ROAD PAVING SCHEDULE


DLS Contracting updated schedule for milling and paving. (Subject to change due to weather) 
 11/11/21: Paving Hudson Avenue and Municipal Complex
 11/13/21: Paving Hickory St (Washington Ave. to George School)
 Respectfully,  Lieutenant Roy J. Scherer
 

10/28/21 - Below is the most recent milling and paving schedule.  Please keep in mind that weather may cause alterations and the work for Palm street has been moved east, just past the entrance of the school:

Wednesday, 11/03/2021

  • Milling - Ridgewood Road

Thursday, 11/04/2021

  • Milling - Bridge Street & Calvin Street

Friday, 11/05/2021

  • Milling - Hickory Street (Ridgewood Rd. side)

Monday, 11/08/2021

  • Milling - Walnut Street, Palm Street & Hickory Street
  • Paving - Ridgewood Road

Tuesday, 11/09/2021

  • Milling - Hudson Avenue & Municipal Complex
  • Paving - Bridge Street & Calvin Street

Wednesday, 11/10/2021

  • Paving - Hickory Road (Ridgewood Rd. side)

Thursday, 11/11/2021

  • Paving - Walnut Street, Palm Street & Hickory Street

Friday, 11/12/2021

  • Paving - Hudson Avenue & Municipal Complex


Streets scheduled for the First Phase of paving in 2021:

Ridgewood Road from Linwood Avenue to East Glen Avenue;

Hudson Avenue;

Bridge Street;

Township Hall Parking Area;

Calvin Street from Maple Avenue to Bergen Avenue;

Hickory Street from Ridgewood Road to northern terminus;

Hickory Street from Washington Avenue to southern terminus;

Palm Street
 

4/7/21 - RIDGEWOOD RD. PAVING PROJECT -  milling and paving on Ridgewood Rd. between Pascack Rd. and Lafayette Ave (up to the Westwood border) on 4/20 - 4/26 from 8:00 am - 5:00 pm daily.  Completed.  
 
11/3/20 - COUNTY ROAD PAVING PROJECT STATUS UPDATE:   Due to many changes with requirements and approvals from NJDOT and the Covid epidemic, the County's paving program did not get started until September.  Unfortunately, they will not be able to complete our resurfacing project until spring 2021.

FY 2020 Municipal Aid Grant Recipients
NJDOT Local Aid & Economic Development Overview

Status Update - 11/3/20 - Milling is complete on all streets listed below, weather permitting paving will procede as scheduled. Completed.

Status Update - 10/19/20:


 
Status Update - 10/14/20

Status Update - 9/23/20


Paving is currently scheduled to begin on or about Monday, August 3, 2020.  Please click here for Notice to Residents regarding this project.
*schedule is subject to change

 
  • Robinwood Road
  • Woodfield Road, North of Finnerty Place
  • Prospect Ave
  • Salem Road
  • Viola Terrace
  • Johnson Place
  • Cosman Street, Ridgewood Road South to end of PSE&G trench
  • Calvin Street, 100 feet South of Sunset Lane to Howard Place - Do not park South of 606 Calvin which is 1 telephone pole North of the intersection at Calvin and Crestwood where the new asphalt meets the old asphalt. This will be outside any staged equipment the contractor might need. 
  • Crestwood Terrace, from Calvin Street to 428 Crestwood

 

WT Paving History - click map to view